Pennsylvania Wrote a Data-Centres-First Curtailment Order on a PJM Tariff That FERC Then Rejected

Pennsylvania’s draft rule to cut data centres first depends on a PJM tariff that FERC rejected eight days later, leaving the order of curtailment to state rulemakings. Utilities, regulators, data-centre owners and lenders in PJM are exposed through 2028.

Produced using Shaping Tomorrow’s six-stage process for converting external change into decision-ready intelligence.
Scanned and filtered by AI. Stress-tested and judged by humans.

The consensus holds that flexibility is now the price of grid access: new data centres will be cut first in a shortage. Beneath it, the rule has no legal home. Pennsylvania’s tentative order makes its duties conditional on FERC approving PJM’s Interim Resource Adequacy Service (IRAS) “as proposed” (Pennsylvania PUC order, 01/10/2026). Eight days later FERC rejected IRAS: provisions “appear to dictate which retail customers taking retail service will be curtailed” (FERC, 09/10/2026). The wholesale call that was to start the cuts is gone; the state rule that would replace it is unwritten. The decision point falls in 2027 to 2028.

Signal Identification

A regulatory pivot: the curtail-first principle survives, but its instrument does not. FERC kept a Large Load defined at “a cumulative peak of 50 MW” and a registry (FERC, 09/10/2026). Pennsylvania’s draft reaches sites from 25 MW (Pennsylvania PUC order, 01/10/2026).

Time horizon: 1-3 years, and it binds 2027 to 2028, shown when Pennsylvania issues its final order without a FERC-approved IRAS tariff, or a second PJM state issues its own curtailment-order rule before PJM refiles. (Milestones: PJM compliance filing due within 30 days of 9 October 2026; Pennsylvania final order planned for 28 January 2027.)
binds 2027 to 2028202620282029
Probability band: Medium (40 to 60%)
Probability band: Medium, 40 to 60%, the chance the signal binds within the window shown above.LowMediumHigh
Geographic / Jurisdictional Scope: Primary: Pennsylvania, then the other PJM states and DC. Spillover: other US grid regions.
PrimaryPennsylvaniaPJM states and DC
SpilloverOther US grid regions
Sectors exposed:
Electric distribution utilitiesState commissionsData-centre developersHyperscale power buyersInfrastructure lenders

What's Changing

FERC’s order kept the 50 MW definition and a registry, rejected the rest of PJM’s package, and required a compliance filing “within 30 days” (FERC, 09/10/2026). Commissioner Rosner said, “We need state regulators to establish clear rules for which customers should be curtailed first” (Utility Dive, 12/10/2026).

Pennsylvania drafted first. Its commission voted 4-0 for a tentative order under which certain large new loads “would be subject to curtailment before other customers” (Pennsylvania PUC, 01/10/2026). The draft’s site test starts at 25 MW, PJM’s accepted definition at 50 MW; the market monitor counts 26.8 GW, or 28.5% of data-centre peak load, below that line (market monitor, 03/09/2026). In August NRDC’s Claire Lang-Ree said few, if any, other states had taken explicit steps to align with PJM’s pending proposals (Canary Media, 20/08/2026).

The monitor puts the 2028/2029 shortfall at 6,831.3 MW and says data-centre load “has resulted in adding $29.4 billion to the cost of capacity” (market monitor, 03/09/2026). On 22 July about 3,800 MW of load moved to back-up power after a line fault, “the largest load transfer PJM has experienced” (PJM, 31/07/2026).

Where the rule stands, and the dated path ahead

Where the rule stands Large Load: 50 MW Accepted by FERC, 9 Oct Registry of large loads Accepted by FERC, 9 Oct IRAS curtail-first call Rejected by FERC, 9 Oct Pennsylvania duties Tentative; final 28 Jan 2027 Dated pathway 1 Oct 2026 Pennsylvania tentative order 9 Oct 2026 FERC rejects IRAS Within 30 days PJM compliance filing 28 Jan 2027 Pennsylvania final order due 2028/2029 Shortfall year: 6,831.3 MW

Source basis: FERC order, Pennsylvania PUC order and the market monitor (dated above). Steps are in date order, not to scale.

Disruption Pathway

Our reading is that the pathway has three stages. Through early 2027 PJM files only the definition and registry (Troutman Energy Report, 21/10/2026), while Pennsylvania takes comments and plans a final order for 28 January 2027 (Pennsylvania PUC order, 01/10/2026). Through 2027 a choice forms: PJM refiles a design that fits FERC’s finding, or states lead a revival, which Jefferies expects (Utility Dive, 12/10/2026). Commissioner Rosner wants any refile to “justify curtailing IRAS load on a mandatory basis” (Troutman Energy Report, 21/10/2026). In 2028 the shortfall year tests whichever order exists.

Stress concentrates at three points. The trigger: with IRAS rejected, our reading is that the Pennsylvania draft has no wholesale call to start its cuts, and the order is silent on a rejection (Pennsylvania PUC order, 01/10/2026). The threshold: 25 MW against 50 MW leaves sites that state and PJM treat differently (market monitor, 03/09/2026). The loads: a July fault moved large loads to back-up power unprompted (PJM, 31/07/2026). Two adaptations follow: commissions write interruptible tariffs that stand without a PJM call, and developers write curtailment terms into interconnection agreements site by site.

Why This Matters Now

State commissions, utility regulatory teams, hyperscale power buyers and project lenders hold this decision. Plans for PJM sites that assume one curtail-first rule should be re-read: its source now differs by state, and today it exists only as a Pennsylvania draft (Pennsylvania PUC order, 01/10/2026). Operators should map planned sites against the 25 MW and 50 MW lines, treat curtailment clauses as state-specific, and comment on Pennsylvania’s draft within 30 days of its Bulletin publication.

Decision-action posture for this signal: Prepare: site maps and state-specific clauses can be built now, while capital that assumes one PJM-wide rule should wait for Pennsylvania’s final order or a refiled tariff.

Counter-Argument

The strongest objection is that this is delay, not defect. FERC offered “guidance on how PJM could modify its proposal” (FERC, 09/10/2026), Jefferies expects the proposal to be “minimally revived in future iterations” (Utility Dive, 12/10/2026), and Pennsylvania’s duties are drafted to bind the day a tariff is approved (Pennsylvania PUC order, 01/10/2026).

Delay is the signal. The conditional draft binds nothing until a tariff exists, and the market monitor argues PJM “improperly defers to the states and EDCs the critical determinations of which customers will be subject to” curtailment (market monitor, 03/09/2026). Our reading is that a refile leaving the choice to states invites the same objection.

Implications

This is a durable change in who writes the rule, with transient mechanics. On the available evidence the inflection window runs from Pennsylvania’s planned final order on 28 January 2027 to the 2028/2029 shortfall year. States and utilities that publish a tested curtailment order early gain a usable position; owners and lenders that priced one PJM-wide term lose, as do sites between 25 MW and 50 MW that the two texts cover unevenly. FERC’s order is the canonical text (FERC, 09/10/2026).

Early Indicators to Monitor

Disconfirming Signals

Strategic Questions

Keywords

Large-load curtailment; Interim Resource Adequacy Service (IRAS); PJM; FERC jurisdiction; retail customers; Pennsylvania Public Utility Commission; data-centre interconnection; state utility regulation; capacity shortfall

Bibliography

Source tiers: Tier 1, governments, regulators and intergovernmental bodies. Tier 2, think-tanks, academic institutes, major consultancies and quality data providers. Tier 3, quality journalism and specialist trade press. Tier 4, vendor, company and practitioner sources, used only as directional corroboration.

How this was made

The Decision-Grade Intelligence Method

Shaping Tomorrow’s six-stage process for converting external change into decision-ready intelligence.

Scan · Filter · Stress-test · Judge · Trigger · Actionable Intelligence

See full methodology → · How we verify → · Track record →


Prepared by Shaping Tomorrow: 27 October 2026